CAPITAL IMPROVEMENTS INCLUDE
- Demolition of single-story annex building along 32nd Place and converted to a secured loading/unloading area
- New construction of a truck court, dock canopy, and elevator cores
- (2) New 5’-8” x 9’-0” freight elevators that can be dedicated to full floor users
- (2) New shared 5’-8” x 9’-0” freight elevators with access to every floor, one of which provides access to parking cellar and roof
- Complete lobby renovation with a new entrance and canopy
- Repainting entire building exterior and window frames for a clean, modern look (COMPLETE)
- Upgrading building to high voltage service of 15W psf, with installation of (4) 2500kVA transformers
- Replacing existing 750kW generator with new 1000kW standby generator (roof space available for a tenant’s dedicated generator)
- Constructing new core restrooms on floors 2 – 5
- New fire alarm system
- Gas lines